Construction Trends - http://www.constructiontrends.com
Mega-Project Lessons Learned: Risk; Document Control; Payments; Public Outreach; Agency Coordination; Audit & Oversight
http://www.constructiontrends.com/articles/6115/1/Mega-Project-Lessons-Learned-Risk-Document-Control-Payments-Public-Outreach-Agency-Coordination-Audit-amp-Oversight/Page1.html
Robert Prieto
Currently - Senior Vice President, Fluor; Industrial & Infrastructure Group; Strategy Previously - Chairman, Parsons Brinckerhoff Inc. 
By Robert Prieto
Published on 03/25/2008
 

The lessons learned that follow are based on experience in the infrastructure, buildings, government, power and industrial sectors on “mega-projects”. “Mega-projects” are those projects which are complex in nature (technically, logistically, politically, etc.) and have total installed costs in excess of $1,000,000,000.


Mega-Project Lessons Learned: Risk; Document Control; Payments; Public Outreach; Agency Coordination; Audit & Oversight

By

Bob Prieto
Senior Vice President
Fluor

The lessons learned that follow are based on experience in the infrastructure, buildings, government, power and industrial sectors on “mega-projects”. “Mega-projects” are those projects which are complex in nature (technically, logistically, politically, etc.) and have total installed costs in excess of $1,000,000,000.

This is the fourth part in a series of such lessons learned. This part addresses lessons learned in:

  • Risk
  • Document Control
  • Payments
  • Public Outreach
  • Agency Coordination
  • Audit & Oversight

The first three parts of this series addressed lessons learned with respect to:

  • Project Management Plan
  • Finance Plan
  • Safety
  • Schedule
  • Cost Estimating
  • Cost, Schedule, and Status Reporting
  • Cost Containment
  • Project Personnel
  • Technical
  • Continuous Improvement
  • Procurement
  • Labor

These lessons learned are not intended to be comprehensive in nature but rather represent a compilation of such lessons that the author has, through his various professional and industry experiences, identified as important to the success of “mega-projects”. Many represent nothing more than the fundamentals of good project management, but because scaling effects are non-linear, they take on special importance on “mega-projects”.

The lessons that are described apply across a full spectrum of delivery and contracting approaches.

Risk

  • establish an integrated risk management program using risk analysis
    • use both deterministic and probabilistic applications
    • carefully monitor the risk bias that can distort risk elements and mitigation plans to be integrated into the project management constraints process (schedules, cost, scope, etc.)
    • risk(s) impacts to be realized in the form of contingencies and reserves
    • rebaseline risk profiles on key milestone phases such as preliminary engineering, final engineering, construction mid-point etc.
  • focus on common risk issues that characteristically include
    • environmental impacts and archeological and historical preservation issues
    • property acquisition and land access
    • existing conditions (geological) and infrastructure (utilities and structures)
  • contract documents allocate risks to the parties who can best control the risk.
  • special requirements of underground risk and contracting reflected in contract documents
  • high risk events should be the subject of “what if” or scenario planning
  • used to track cost saving opportunities
  • cost and schedule risk analysis
  • clear assignment of staff responsibility for risk mitigation
  • quantitative and qualitative risk assessments
  • continuous monitoring of risk mitigation
  • include WORSE CASE SCENARIOS
  • do not try to transfer a risk that is not fully understood by all parties

Document Control

  • meetings on document control, e-mail and electronic drawing procedures and the understanding of how these will work as a project communication tool held at outset of project
  • field test all document control processes, procedures and tools at the earliest possible stages of the project
  • scanned drawings should be saved as .jpeg of .gif formats instead of .tif to facilitate transmission
  • email archiving (sent/received) provides foundation for dispute resolution and litigation and audit support
  • establish a document control system that can efficiently retrieve information in a timely way
  • have the IT support for using as much graphic material as possible….one good picture can replace an engineers thousand words
  • QA/QC program includes to include document control
  • data base management of documents, revisions, configuration , tracking for who’s “court is the ball in

Payments

  • Agencies utilizing federal funding must obtain prior approval on making mobilization or advanced payments
  • Agencies utilizing federal funds are required to implement certain requirements when utilizing progress payments.
  • ensure payment flow-downs through payment bonds, credit reports, or other available validation
  • plan for and maintain a positive cash-flow and expenditure plan
  • ensure that all payment and expenditure procedures will support a rigid audit trail
  • be very clear about the criteria for retainage, award fees, etc.
  • ensure certification of payment transactions

Public Outreach

  • comprehensive program….never saw one that did too much
  • good identification of issues important to stakeholders
  • recognize “buy America” perception requirement on all highly visible government funded projects (higher standard than contract language) KEEP THE PUBLIC INFORMED
  • be responsive to public concerns
  • demonstrate a proactive public protection of property and person
  • facilitate public interaction groups

Agency Coordination

  • owner, engineer and construction manager should all be in attendance at agency coordination meetings
  • regular meetings should be scheduled as well as issue oriented sessions
    • helps bring agencies along in the project evolution process
    • creates an engaged stakeholder focused on problem resolution rather than posturing
    • improves quality of planning by agency/program or construction manager/ owner

Audit & Oversight

  • funding agency should make annual independent cost-to-complete estimates
    • differences with CM estimate should be reviewed and reconciled as part of normal management process
  • independent audits should be coordinated to facilitate a team approach to auditing
    • improves quality of the audit product
    • minimizes project disruption
    • team approach limits role of “personalities”
    • improved auditing checklist evolves minimizing surprises
  • successful audit programs focus on priority areas, non-conformances and systemic problems
  • audit programs should foster continuous improvement and be based on ongoing risk analyses
  • compliance auditing programs similar to those called out in ISO 10011-3-94 produce good results
  • financial strength of major contractors is a leading indicator on their ability to execute large, complex programs (if they can’t manage their own business how will they manage the client’s)
  • major or high visibility programs will attract IG’s from funding agencies
    • project should plan and staff to meet their needs
  • timely follow-up on all audit findings