Mega-Project Lessons Learned: Risk; Document Control; Payments; Public Outreach; Agency Coordination; Audit & Oversight
By
Bob Prieto
Senior Vice President
Fluor
The lessons learned that follow are based on experience in the infrastructure, buildings, government, power and industrial sectors on “mega-projects”. “Mega-projects” are those projects which are complex in nature (technically, logistically, politically, etc.) and have total installed costs in excess of $1,000,000,000.
This is the fourth part in a series of such lessons learned. This part addresses lessons learned in:
- Risk
- Document Control
- Payments
- Public Outreach
- Agency Coordination
- Audit & Oversight
The first three parts of this series addressed lessons learned with respect to:
- Project Management Plan
- Finance Plan
- Safety
- Schedule
- Cost Estimating
- Cost, Schedule, and Status Reporting
- Cost Containment
- Project Personnel
- Technical
- Continuous Improvement
- Procurement
- Labor
These lessons learned are not intended to be comprehensive in nature but rather represent a compilation of such lessons that the author has, through his various professional and industry experiences, identified as important to the success of “mega-projects”. Many represent nothing more than the fundamentals of good project management, but because scaling effects are non-linear, they take on special importance on “mega-projects”.
The lessons that are described apply across a full spectrum of delivery and contracting approaches.
Risk
- establish an integrated risk management program using risk analysis
- use both deterministic and probabilistic applications
- carefully monitor the risk bias that can distort risk elements and mitigation plans to be integrated into the project management constraints process (schedules, cost, scope, etc.)
- risk(s) impacts to be realized in the form of contingencies and reserves
- rebaseline risk profiles on key milestone phases such as preliminary engineering, final engineering, construction mid-point etc.
- focus on common risk issues that characteristically include
- environmental impacts and archeological and historical preservation issues
- property acquisition and land access
- existing conditions (geological) and infrastructure (utilities and structures)
- contract documents allocate risks to the parties who can best control the risk.
- special requirements of underground risk and contracting reflected in contract documents
- high risk events should be the subject of “what if” or scenario planning
- used to track cost saving opportunities
- cost and schedule risk analysis
- clear assignment of staff responsibility for risk mitigation
- quantitative and qualitative risk assessments
- continuous monitoring of risk mitigation
- include WORSE CASE SCENARIOS
- do not try to transfer a risk that is not fully understood by all parties
Document Control
- meetings on document control, e-mail and electronic drawing procedures and the understanding of how these will work as a project communication tool held at outset of project
- field test all document control processes, procedures and tools at the earliest possible stages of the project
- scanned drawings should be saved as .jpeg of .gif formats instead of .tif to facilitate transmission
- email archiving (sent/received) provides foundation for dispute resolution and litigation and audit support
- establish a document control system that can efficiently retrieve information in a timely way
- have the IT support for using as much graphic material as possible….one good picture can replace an engineers thousand words
- QA/QC program includes to include document control
- data base management of documents, revisions, configuration , tracking for who’s “court is the ball in
Payments
- Agencies utilizing federal funding must obtain prior approval on making mobilization or advanced payments
- Agencies utilizing federal funds are required to implement certain requirements when utilizing progress payments.
- ensure payment flow-downs through payment bonds, credit reports, or other available validation
- plan for and maintain a positive cash-flow and expenditure plan
- ensure that all payment and expenditure procedures will support a rigid audit trail
- be very clear about the criteria for retainage, award fees, etc.
- ensure certification of payment transactions
Public Outreach
- comprehensive program….never saw one that did too much
- good identification of issues important to stakeholders
- recognize “buy America” perception requirement on all highly visible government funded projects (higher standard than contract language) KEEP THE PUBLIC INFORMED
- be responsive to public concerns
- demonstrate a proactive public protection of property and person
- facilitate public interaction groups
Agency Coordination
- owner, engineer and construction manager should all be in attendance at agency coordination meetings
- regular meetings should be scheduled as well as issue oriented sessions
- helps bring agencies along in the project evolution process
- creates an engaged stakeholder focused on problem resolution rather than posturing
- improves quality of planning by agency/program or construction manager/ owner
Audit & Oversight
- funding agency should make annual independent cost-to-complete estimates
- differences with CM estimate should be reviewed and reconciled as part of normal management process
- independent audits should be coordinated to facilitate a team approach to auditing
- improves quality of the audit product
- minimizes project disruption
- team approach limits role of “personalities”
- improved auditing checklist evolves minimizing surprises
- successful audit programs focus on priority areas, non-conformances and systemic problems
- audit programs should foster continuous improvement and be based on ongoing risk analyses
- compliance auditing programs similar to those called out in ISO 10011-3-94 produce good results
- financial strength of major contractors is a leading indicator on their ability to execute large, complex programs (if they can’t manage their own business how will they manage the client’s)
- major or high visibility programs will attract IG’s from funding agencies
- project should plan and staff to meet their needs
- timely follow-up on all audit findings