- Home
- Construction Management
- Mega-Project Lessons Learned: Risk; Document Control; Payments; Public Outreach; Agency Coordination; Audit & Oversight
Mega-Project Lessons Learned: Risk; Document Control; Payments; Public Outreach; Agency Coordination; Audit & Oversight
- By Robert Prieto
- Published 03/25/2008
- Construction Management
- Unrated
Robert Prieto
Currently - Senior Vice President, Fluor; Industrial & Infrastructure Group; Strategy Previously - Chairman, Parsons Brinckerhoff Inc.
View all articles by Robert PrietoBy
Bob Prieto
Senior Vice President
Fluor
The lessons learned that follow are based on experience in the infrastructure, buildings, government, power and industrial sectors on “mega-projects”. “Mega-projects” are those projects which are complex in nature (technically, logistically, politically, etc.) and have total installed costs in excess of $1,000,000,000.
This is the fourth part in a Series of such lessons learned. This part addresses lessons learned in:
- Risk
- Document Control
- Payments
- Public Outreach
- Agency Coordination
- Audit & Oversight
The first three parts of this series addressed lessons learned with respect to:
- Project Management Plan
- Finance Plan
- Safety
- Schedule
- Cost Estimating
- Cost, Schedule, and Status Reporting
- Cost Containment
- Project Personnel
- Technical
- Continuous Improvement
- Procurement
- Labor
These lessons learned are not intended to be comprehensive in nature but rather represent a compilation of such lessons that the author has, through his various professional and industry experiences, identified as important to the success of “mega-projects”. Many represent nothing more than the fundamentals of good project management, but because scaling effects are non-linear, they take on special importance on “mega-projects”.
The lessons that are described apply across a full spectrum of delivery and contracting approaches.
Risk
- establish an integrated risk management program using risk analysis
- use both deterministic and probabilistic applications
- carefully monitor the risk bias that can distort risk elements and mitigation plans to be integrated into the project management constraints process (schedules, cost, scope, etc.)
- risk(s) impacts to be realized in the form of contingencies and reserves
- rebaseline risk profiles on key milestone phases such as preliminary engineering, final engineering, construction mid-point etc.
- focus on common risk issues that characteristically include
- environmental impacts and archeological and historical preservation issues
- property acquisition and land access
- existing conditions (geological) and infrastructure (utilities and structures)
- contract documents allocate risks to the parties who can best control the risk.
- special requirements of underground risk and contracting reflected in contract documents
- high risk events should be the subject of “what if” or scenario planning
- used to track cost saving opportunities
- cost and schedule risk analysis
- clear assignment of staff responsibility for risk mitigation
- quantitative and qualitative risk assessments
- continuous monitoring of risk mitigation
- include WORSE CASE SCENARIOS
- do not try to transfer a risk that is not fully understood by all parties
Document Control
- meetings on document control, e-mail and electronic drawing procedures and the understanding of how these will work as a project communication tool held at outset of project
- field test all document control processes, procedures and tools at the earliest possible stages of the project
- scanned drawings should be saved as .jpeg of .gif formats instead of .tif to facilitate transmission
- email archiving (sent/received) provides foundation for dispute resolution and litigation and audit support
- establish a document control system that can efficiently retrieve information in a timely way
- have the IT support for using as much graphic material as possible….one good picture can replace an engineers thousand words
- QA/QC program includes to include document control
- data base management of documents, revisions, configuration , tracking for who’s “court is the ball in
Payments
- Agencies utilizing federal funding must obtain prior approval on making mobilization or advanced payments
- Agencies utilizing federal funds are required to implement certain requirements when utilizing progress payments.
- ensure payment flow-downs through payment bonds, credit reports, or other available validation
- plan for and maintain a positive cash-flow and expenditure plan
- ensure that all payment and expenditure procedures will support a rigid audit trail
- be very clear about the criteria for retainage, award fees, etc.
- ensure certification of payment transactions
Public Outreach
- comprehensive program….never saw one that did too much
- good identification of issues important to stakeholders
- recognize “buy America” perception requirement on all highly visible government funded projects (higher standard than contract language) KEEP THE PUBLIC INFORMED
- be responsive to public concerns
- demonstrate a proactive public protection of property and person
- facilitate public interaction groups
Agency Coordination
- owner, engineer and construction manager should all be in attendance at agency coordination meetings
- regular meetings should be scheduled as well as issue oriented sessions
- helps bring agencies along in the project evolution process
- creates an engaged stakeholder focused on problem resolution rather than posturing
- improves quality of planning by agency/program or construction manager/ owner
Audit & Oversight
- funding agency should make annual independent cost-to-complete estimates
- differences with CM estimate should be reviewed and reconciled as part of normal management process
- independent audits should be coordinated to facilitate a team approach to auditing
- improves quality of the audit product
- minimizes project disruption
- team approach limits role of “personalities”
- improved auditing checklist evolves minimizing surprises
- successful audit programs focus on priority areas, non-conformances and systemic problems
- audit programs should foster continuous improvement and be based on ongoing risk analyses
- compliance auditing programs similar to those called out in ISO 10011-3-94 produce good results
- financial strength of major contractors is a leading indicator on their ability to execute large, complex programs (if they can’t manage their own business how will they manage the client’s)
- major or high visibility programs will attract IG’s from funding agencies
- project should plan and staff to meet their needs
- timely follow-up on all audit findings
Subscribe, Share, Bookmark This Story:
Article Series
-
Mega-Project Lessons Learned: Risk; Document Control; Payments; Public Outreach; Agency Coordination; Audit & Oversight
