Mega-Project Lessons Learned: Project Management Plan; Finance Plan; Safety; Schedule
By
Bob Prieto
Senior Vice President
Fluor Corporation
The lessons learned that follow are based on experience in the infrastructure, buildings, government, power and industrial sectors on “mega-projects”. “Mega-projects” are those projects which are complex in nature (technically, logistically, politically, etc.) and have total installed costs in excess of $1,000,000,000. These lessons learned are not intended to be comprehensive in nature but rather represent a compilation of such lessons that the author has, through his various professional and industry experiences, identified as important to the success of “mega-projects”. Many represent nothing more than the fundamentals of good project management, but because scaling effects are non-linear, they take on special importance on “mega-projects”.
The lessons that are described apply across a full spectrum of delivery and contracting approaches and are supplemented by additional observations and considerations for Public-Private-Partnerships (PPP) and Design-Build projects which appear at the end of this series.
This series will encompass the following subject areas in five parts.
Part 1
Project Management Plan
Finance Plan
Safety
Schedule
Part 2
Cost Estimating
Cost, Schedule, and Status Reporting
Cost Containment
Project Personnel
Part 3
Technical
Continuous Improvement
Procurement
Labor
Part 4
Risk
Document Control
Payments
Public Outreach
Agency Coordination
Audit & Oversight
Part 5
PPP or Public Private Partnerships
PPP Lessons Learned – Government
PPP Lessons Learned – Developer-Contractor
Design Build
Design Build Lessons Learned – Agency
Part 1
Project Management Plan
- developed early
- capture project goals, objectives and scope definition
- identify budget plan….reconfirm reasonableness
- identify constraints, threats and opportunities
- clearly define roles, responsibilities, processes, activities and authority which will result in project success
- integration and interface management are key
- rapid decision making is key (what is a minute in the field worth)
- $1,000,000,000 is about $2,000 per minute for 24/365 construction
- comprehensively linked to contract requirements and provisions
- well developed project management system including project specific plan, general corporate project management manual, supporting procedures fully integrated into standard company approach, fully integrated project and construction management tool set
- change order and claims controls and other cost containment strategies to be used throughout the life of the project clearly defined.
- signed off by highest levels of management
- project scope, budget and schedule are not artificially constrained (wishing does not make it so) and recognize that everything will not go according to plan
- on highly sensitive projects (environmental, burial grounds, native lands etc.), a monitoring team should be established with input and buy-in from involved stakeholders to proactively provide guidance and resolve concerns before they impact the project schedule.
- make sure archeological and historical preservation issues thoroughly addressed early on
- Owner Controlled Insurance Programs (OCIP) should be used
- improves safety performance
- improves risk insurance administration and management
- client’s internal project management oversight is used as a positive management tool, making constructive contributions…not in an adversarial way
- program and construction mangers conduct annual bottoms up review of team’s self performance
- must recognize that mega projects are subject to a higher and more comprehensive auditing standard and must build in the necessary resources and time for such processes
- document control for audit and litigation support is a requirement of large projects and must be adequately staffed and budgeted
- kickoff of each project phase should include a session of all relevant lessons learned
- should emphasize importance of capturing lessons learned contemporaneously
- should involve all key project stakeholders
- soft project objectives such as SB/DBE contracting; technology transfer; local craft training; etc need to be built into plan and schedule at outset of project
- partnering plan provides for periodic sessions
- ensure constraints of right-of-way and property acquisition and access agreements are completely reflected in project schedule, management and work processes, and means and methods
- review clarity of responsibilities and authorities throughout the project to ensure no ambiguity or unintended delegations
- establish criteria for ensuring adequate technical capacity and capabilities exist
- provide security protocols for design and construction (without revealing sensitive areas or vulnerabilities
- ensure schedule reflects impact of access and egress from secure areas
- be clear on any equipment limitations in secure areas or limits on means and methods in those areas
- to change outcomes you need to change strategy
Finance Plan
- credible plan to finance the project must be in place at the start of construction.
- avoid cost growth associated with start and stop construction.
- financial management systems for receiving, approving and paying supplier and subcontractor invoices must be comprehensive on mega-projects and provide for linkage to purchase orders, contracts and proof of receipt of materials or accepted completion of work
- code of accounts and project WBS should map
- have a defined and detailed process for contract final audit and closeout
- revalidate adequacy of financial controls and processes at key points throughout the project
Safety
- safety must be a primary focus
- safe work site more efficient than unsafe one
- perform a safety hazard analysis at the beginning of each milestone phase (preliminary engineering, final design, construction, and commissioning)
- make safety a selection criteria….give it substantial weight
- requalify contractors based on performance
- incentive safe execution in contractor risk/reward program
- start every project meeting with a safety topic (and a value creation topic)
- top management to walk job site daily for a safety check
- safety incentives should extend down to the subcontractor or laborer level
- cultivate a project safety conscience environment through safety workshops, posters of safety procedures, incidents rates, etc
- office safety
- field investigation safety
- frequent “tool box” safety sessions
- health and personnel accident prevention issues addressed
- crane safety requirements are heightened on sites with multiple contractors
- never lower into blind areas
- never assume movement path and laydown areas are safe
- never allow load to be out of control
- clearly identify construction hazard zones
Schedule
- well developed and documented schedule logic, basis, and assumptions
- utilize 4D visualization to review complex construction sequencing operations
- establish a comprehensive schedule network following the WBS
- flexible contractor interfaces to accommodate mitigation of potential delays
- adequate float to accommodate unknowns…float managed as a scarce resource
- continuous trend identification and analysis using earned value techniques
- critical path clearly identified
- incorporate contractor’s detailed schedule in overall site construction schedules for logistically complex projects
- ensure acceptance testing and inspection reflected on schedule
- ongoing schedule risk analysis
- keep schedule revisions current
- utilize integrated project schedules incorporating cost, time and risk contingencies
- integrate schedule constraints that are external to the project control
- identify alternative paths of execution
- rebaseline at well defined milestone phases (i.e. completeness of final design, mid-point of construction, etc.)
- always track against baseline target