- Home
- Construction Management
- Mega-Project Lessons Learned: Project Management Plan; Finance Plan; Safety; Schedule
Mega-Project Lessons Learned: Project Management Plan; Finance Plan; Safety; Schedule
- By Robert Prieto
- Published 03/10/2008
- Construction Management
- Unrated
| Tweet | Share |
Robert Prieto
Currently - Senior Vice President, Fluor; Industrial & Infrastructure Group; Strategy Previously - Chairman, Parsons Brinckerhoff Inc.
View all articles by Robert PrietoBy
Bob Prieto
Senior Vice President
Fluor Corporation
The lessons learned that follow are based on experience in the infrastructure, buildings, government, power and industrial sectors on “mega-projects”. “Mega-projects” are those projects which are complex in nature (technically, logistically, politically, etc.) and have total installed costs in excess of $1,000,000,000. These lessons learned are not intended to be comprehensive in nature but rather represent a compilation of such lessons that the author has, through his various professional and industry experiences, identified as important to the success of “mega-projects”. Many represent nothing more than the fundamentals of good project management, but because scaling effects are non-linear, they take on special importance on “mega-projects”.
The lessons that are described apply across a full spectrum of delivery and contracting approaches and are supplemented by additional observations and considerations for Public-Private-Partnerships (PPP) and Design-Build projects which appear at the end of this Series.
This series will encompass the following subject areas in five parts.
Part 1
Project Management Plan
Finance Plan
Safety
Schedule
Part 2
Cost Estimating
Cost, Schedule, and Status Reporting
Cost Containment
Project Personnel
Part 3
Technical
Continuous Improvement
Procurement
Labor
Part 4
Risk
Document Control
Payments
Public Outreach
Agency Coordination
Audit & Oversight
Part 5
PPP or Public Private Partnerships
PPP Lessons Learned – Government
PPP Lessons Learned – Developer-Contractor
Design Build
Design Build Lessons Learned – Agency
Part 1
Project Management Plan
- developed early
- capture project goals, objectives and scope definition
- identify budget plan….reconfirm reasonableness
- identify constraints, threats and opportunities
- clearly define roles, responsibilities, processes, activities and authority which will result in project success
- integration and interface management are key
- rapid decision making is key (what is a minute in the field worth)
- $1,000,000,000 is about $2,000 per minute for 24/365 construction
- comprehensively linked to contract requirements and provisions
- well developed project management system including project specific plan, general corporate project management manual, supporting procedures fully integrated into standard company approach, fully integrated project and construction management tool set
- change order and claims controls and other cost containment strategies to be used throughout the life of the project clearly defined.
- signed off by highest levels of management
- project scope, budget and schedule are not artificially constrained (wishing does not make it so) and recognize that everything will not go according to plan
- on highly sensitive projects (environmental, burial grounds, native lands etc.), a monitoring team should be established with input and buy-in from involved stakeholders to proactively provide guidance and resolve concerns before they impact the project schedule.
- make sure archeological and historical preservation issues thoroughly addressed early on
- Owner Controlled Insurance Programs (OCIP) should be used
- improves safety performance
- improves risk insurance administration and management
- client’s internal project management oversight is used as a positive management tool, making constructive contributions…not in an adversarial way
- program and construction mangers conduct annual bottoms up review of team’s self performance
- must recognize that mega projects are subject to a higher and more comprehensive auditing standard and must build in the necessary resources and time for such processes
- document control for audit and litigation support is a requirement of large projects and must be adequately staffed and budgeted
- kickoff of each project phase should include a session of all relevant lessons learned
- should emphasize importance of capturing lessons learned contemporaneously
- should involve all key project stakeholders
- soft project objectives such as SB/DBE contracting; technology transfer; local craft training; etc need to be built into plan and schedule at outset of project
- partnering plan provides for periodic sessions
- ensure constraints of right-of-way and property acquisition and access agreements are completely reflected in project schedule, management and work processes, and means and methods
- review clarity of responsibilities and authorities throughout the project to ensure no ambiguity or unintended delegations
- be clear
- establish criteria for ensuring adequate technical capacity and capabilities exist
- provide Security protocols for design and construction (without revealing sensitive areas or vulnerabilities
- ensure schedule reflects impact of access and egress from secure areas
- be clear on any equipment limitations in secure areas or limits on means and methods in those areas
- to change outcomes you need to change strategy
Finance Plan
- credible plan to finance the project must be in place at the start of construction.
- avoid cost growth associated with start and stop construction.
- financial management systems for receiving, approving and paying supplier and subcontractor invoices must be comprehensive on mega-projects and provide for linkage to purchase orders, contracts and proof of receipt of materials or accepted completion of work
- code of accounts and project WBS should map
- have a defined and detailed process for contract final audit and closeout
- revalidate adequacy of financial controls and processes at key points throughout the project
Safety
- safety must be a primary focus
- safe work site more efficient than unsafe one
- perform a safety hazard analysis at the beginning of each milestone phase (preliminary engineering, final design, construction, and commissioning)
- make safety a selection criteria….give it substantial weight
- requalify contractors based on performance
- incentive safe execution in contractor risk/reward program
- start every project meeting with a safety topic (and a value creation topic)
- top management to walk job site daily for a safety check
- safety incentives should extend down to the subcontractor or laborer level
- cultivate a project safety conscience environment through safety workshops, posters of safety procedures, incidents rates, etc
- office safety
- field investigation safety
- frequent “tool box” safety sessions
- health and personnel accident prevention issues addressed
- crane safety requirements are heightened on sites with multiple contractors
- never lower into blind areas
- never assume movement path and laydown areas are safe
- never allow load to be out of control
- clearly identify construction hazard zones
Schedule
- well developed and documented schedule logic, basis, and assumptions
- utilize 4D visualization to review complex construction sequencing operations
- establish a comprehensive schedule network following the WBS
- flexible contractor interfaces to accommodate mitigation of potential delays
- adequate float to accommodate unknowns…float managed as a scarce resource
- continuous trend identification and analysis using earned value techniques
- critical path clearly identified
- incorporate contractor’s detailed schedule in overall site construction schedules for logistically complex projects
- ensure acceptance testing and inspection reflected on schedule
- ongoing schedule risk analysis
- keep schedule revisions current
- utilize integrated project schedules incorporating cost, time and risk contingencies
- integrate schedule constraints that are external to the project control
- identify alternative paths of execution
- rebaseline at well defined milestone phases (i.e. completeness of final design, mid-point of construction, etc.)
- always track against baseline target
Subscribe, Share, Bookmark This Story:
Article Series
-
Mega-Project Lessons Learned: Project Management Plan; Finance Plan; Safety; Schedule

